Sunday 5 April 2020

Rotunda March 2020

Well, our rotunda that we had wanted in time for our Yacht Club Ball is back on track

In fact the reason for the Yacht Club Ball was the rotunda

So it was disappointing that it wasn't done in time

We had started talking about it last September, spoken to a couple of specialist builders, decided on one of them, decided on which rotunda, which features, colours etc

Was organising some of this from our hotel room in Adelaide last November before our Ghan trip

Anyway, had to go through the tedium and expense of first a Planning permit and then a Building permit which I did through Loddon Council

Obviously Christmas/New Year interrupted this a little, and I was dealing with them in early January while on Koh Samui for our family holiday

All the while thinking that yes, we would get it in time

The planning permit was approved on 21 January - which I thought was great

The building permit ended up being approved  around 11 February, so we thought we were still in with a good chance

However the building permit was granted with several over engineered provisos which not only added extra time but more expense... arghhh

Anyway, it started up on 24 March as per below

And here is its progress - photos provided by Tom

Sorting out position


Where we want the entrance


in relation to the house/bay window


Digging out the overflow ditch, and also flattening some of the surrounding ground


And the pipe
Uprights



And a roof frame